A set of jobs U, V, W, X, Y, Z arrive at time to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.
The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is
A
W-X-Z-V-Y-U
B
W-X-V-Z-Y-U
C
W-U-Z-V-Y-X
D
U-Y-V-Z-X-W

Correct : b

Similar Questions

After playing _________ hours of tennis, I am feeling _________ tired to walk back.
#1 MCQ
The average of the monthly salaries of M, N and S is ₹ 4000. The average of the monthly salaries of N, S and P is ₹ 5000. The monthly salary of P is ₹ 6000.What...
#2 MCQ
A person travelled 80 km in 6 hours. If the person travelled the first part with a uniform speed of 10 kmph and the remaining part with a uniform speed of 18kmp...
#3 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......