Mechanical Engineering > GATE 2022 SET-2 > Machining
Parts P1-P7 are machined first on a milling machine and then polished at a separate
machine. Using the information in the following table, the minimum total
completion time required for carrying out both the operations for all 7 parts
is __________ hours.


Correct : c