Mechanical Engineering > GATE 2022 SET-1 > Operations Research
An assignment problem is solved to minimize the total processing time of four jobs (1, 2, 3 and 4) on four different machines such that each job is processed exactly by one machine and each machine processes exactly one job. The minimum total processing time is found to be 500 minutes. Due to a change in design, the processing time of Job 4 on each machine has increased by 20 minutes. The revised minimum total processing time will be _____________ minutes (in integer).
Correct : 520
Similar Questions
A linear programming problem is shown below.Maximize 3x + 7ySubject to3x + 7y ≤ 104x + 6y ≤ 8x, y ≥ 0It has
A linear programming problem is shown below.Maximize 3x + 7ySubject to3x + 7y ≤ 104x + 6y ≤ 8x, y ≥ 0It has
After playing _________ hours of tennis, I am feeling _________ tired to walk back.
Total Unique Visitors
Loading......