Mechanical Engineering > GATE 2022 SET-1 > Project Management
Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ____________ hours.
A
5
B
10
C
8
D
9

Correct : c

Similar Questions

A project has four activities P, Q, R and S as shown below: The normal cost of the project is Rs. 10,000 and the overhead cost is Rs. 200/day. If the project...
#477 Fill in the Blanks
A project has four activities P, Q, R and S as shown below: The normal cost of the project is Rs. 10,000 and the overhead cost is Rs. 200/day. If the project...
#477 Fill in the Blanks
A project has four activities P, Q, R and S as shown below: The normal cost of the project is Rs. 10,000 and the overhead cost is Rs. 200/day. If the project...
#477 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......