It was estimated that 52 men can complete a strip in a newly constructed highway Q.2 connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?
A
13 days
B
5 days
C
10 days
D
3 days

Explanation

Correct : d