It was estimated that 52 men can complete a strip in a newly constructed highway Q.2
connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another
project. How many number of days, more than the original estimate, will be required
to complete the strip?
Explanation
Correct : d