Mechanical Engineering > Gate 2018 Set-2 > Quants
A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?
A
50
B
89
C
146
D
7

Correct : d

Similar Questions

A rhombus is formed by joining the midpoints of the sides of a unit square.What is the diameter of the largest circle that can be inscribed within the rhombus?
#6 MCQ
An equilateral triangle, a square and a circle have equal areas.What is the ratio of the perimeters of the equilateral triangle to square to circle?
#7 MCQ
In a 12-hour clock that runs correctly, how many times do the second, minute, and hour hands of the clock coincide, in a 12-hour duration from 3 PM in a day to...
#9 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......