A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?
A
50
B
89
C
146
D
7

Correct : d

Similar Questions

A rhombus is formed by joining the midpoints of the sides of a unit square.What is the diameter of the largest circle that can be inscribed within the rhombus?
#6 MCQ
An equilateral triangle, a square and a circle have equal areas.What is the ratio of the perimeters of the equilateral triangle to square to circle?
#7 MCQ
In a 12-hour clock that runs correctly, how many times do the second, minute, and hour hands of the clock coincide, in a 12-hour duration from 3 PM in a day to...
#9 MCQ

Related Topics

work completion mechanical engineering GATE Mechanical Engineering 2018 robots work calculation additional robots required hourly robot operational time work efficiency GATE mechanical engineering gate questions work and time problems

Unique Visitor Count

Total Unique Visitors

Loading......