Mechanical Engineering > GATE 2017 SET-2 > Project Management (PERT/CPM)
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
ActivityImmediate predecessorDuration (days)
A-4
BA3
CA7
DB14
EC4
FD, E9

The minimum project completion time (in days) is ________.

Correct : 30

Similar Questions

A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in...
#1144 Fill in the Blanks
In PERT chart, the activity time distribution is
#1179 MCQ
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.ActivityDuration (days)1-222...
#1233 MCQ

Related Topics

project scheduling mechanical engineering GATE Mechanical Engineering 2017 project completion time activity network diagram minimum project duration mechanical engineering gate precedence relation activities calculate project completion time

Unique Visitor Count

Total Unique Visitors

Loading......