Mechanical Engineering > GATE 2017 SET-2 > Project Management (PERT/CPM)
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
ActivityImmediate predecessorDuration (days)
A-4
BA3
CA7
DB14
EC4
FD, E9

The minimum project completion time (in days) is ________.

Correct : 30