Mechanical Engineering > GATE 2017 SET-1 > Linear Programming
Two models, P and Q, of a product earn profits of Rs. 100 and Rs. 80 per piece, respectively. Production times for P and Q are 5 hours and 3 hours, respectively, while the total production time available is 150 hours. For a total batch size of 40, to maximize profit, the number of units of P to be produced is ________.
Correct : 15
Similar Questions
At the current basic feasible solution (bfs) v0 (v0 β β5), the simplex method yields the following form of a linear programming problem in standard form.
min...
Which one of the options given represents the feasible region of the linear programming model: Maximize
A manufacturing unit produces two products P1 and P2. For each piece of P1 and
P2, the table below provides quantities of materials M1, M2, and M3 required, a...