Mechanical Engineering > GATE 2016 SET-2 > Project Management (PERT/CPM)
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is ________.


Correct : 14