Mechanical Engineering > GATE 2016 SET-1 > Quantitative Aptitude
P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days. R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project?
A
10:11
B
11:10
C
20:21
D
21:20

Correct : c

Similar Questions

A window is made up of a square portion and an equilateral triangle portion above it. The base of the triangular portion coincides with the upper side of the sq...
#1084 MCQ
A window is made up of a square portion and an equilateral triangle portion above it. The base of the triangular portion coincides with the upper side of the sq...
#1084 MCQ
A window is made up of a square portion and an equilateral triangle portion above it. The base of the triangular portion coincides with the upper side of the sq...
#1084 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......