Mechanical Engineering > GATE 2015 SET-2 > Project Management (PERT/CPM)
A project consists of 7 activities. The network along with the time durations (in days) for various activities is shown in the figure. The minimum time (in days) for completion of the project is ________.


Correct : 40
Similar Questions
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:ActivityImmedi...
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in...
In PERT chart, the activity time distribution is