Mechanical Engineering > GATE 2015 SET-2 > Casting
A cube and a sphere made of cast iron (each of volume 1000 cm3) were cast under identical conditions. The time taken for solidifying the cube was 4 s. The solidification time (in s) for the sphere is ________.

Correct : 6.15

Similar Questions

The allowance provided to a pattern for easy withdrawal from a sand mold is
#188 MCQ
Aluminium is casted in a cube-shaped mold having dimensions as 20 m m × 20 m m × 20 mm. Another mold of the same mold material is used to cast a sphere of alumi...
#204 Fill in the Blanks
In a metal casting process to manufacture parts, both patterns and moulds provide shape by dictating where the material should or should not go. Which of the op...