Mechanical Engineering > GATE 2015 SET-1 > Project Management (PERT/CPM)
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.
ActivityDuration (days)
1-22
2-31
4-33
1-43
2-53
3-52
4-54
The critical path (CP) in the network is
A
1-2-3-5
B
1-4-3-5
C
1-2-3-4-5
D
1-4-5

Correct : b