Match the following products with preferred manufacturing processes:
ProductProcess
P. Rails1. Blow molding
Q. Engine crankshaft2. Extrusion
R. Aluminium channels3. Forging
S. PET water bottles4. Rolling
A
P-4, Q-3, R-1, S-2
B
P-4, Q-3, R-2, S-1
C
P-2, Q-4, R-3, S-1
D
P-3, Q-4, R-2, S-1

Correct : b

Similar Questions

After playing _________ hours of tennis, I am feeling _________ tired to walk back.
#1 MCQ
The average of the monthly salaries of M, N and S is ₹ 4000. The average of the monthly salaries of N, S and P is ₹ 5000. The monthly salary of P is ₹ 6000.What...
#2 MCQ
A person travelled 80 km in 6 hours. If the person travelled the first part with a uniform speed of 10 kmph and the remaining part with a uniform speed of 18kmp...
#3 MCQ

Related Topics

product manufacturing processes mechanical engineering gate 2015 rail manufacturing process crankshaft manufacturing aluminium channel forging PET water bottles rolling extrusion application blow molding applications

Unique Visitor Count

Total Unique Visitors

Loading......