A cylindrical riser of 6 cm diameter and 6 cm height has to be designed for a sand casting mould for producing a steel rectangular plate casting of 7 cm ร— 10 cm ร— 2 cm dimensions having the total solidification time of 1.36 minute. The total solidification time (in minute) of the riser is ________.

Correct : 3.0