The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are
ActivityPredecessorsDuration (days)
a-2
b-4
ca2
db3
ec2
fc4
gd, e5
A
0 and 4
B
1 and 4
C
2 and 3
D
3 and 2

Correct : b