Mechanical Engineering > GATE 2014 SET-3 > Linear Programming
Consider an objective function Z(x1, x2) = 3x1 + 9x2 and the constraints
x1 + x2 ≤ 8,
x1 + 2x2 ≤ 4,
x1 ≥ 0, x2 ≥ 0.
The maximum value of the objective function is _______
x1 + x2 ≤ 8,
x1 + 2x2 ≤ 4,
x1 ≥ 0, x2 ≥ 0.
The maximum value of the objective function is _______
Explanation
Correct : 17 to 19