A project has four activities P, Q, R and S as shown below:
The normal cost of the project is Rs. 10,000 and the overhead cost is Rs. 200/day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is _______

Explanation

Correct : 12500