Mechanical Engineering > GATE 2014 SET-2 > Project Management
A project has four activities P, Q, R and S as shown below:
The normal cost of the project is Rs. 10,000 and the overhead cost is Rs. 200/day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is _______

Correct : 12500

Similar Questions

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the pro...
#299 MCQ
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is ______ hours (ans...
#1393 NAT
After playing _________ hours of tennis, I am feeling _________ tired to walk back.
#1 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......