The current erection cost of a structure is Rs. 13,200. If the labour wages per day increase by 1/5 of the current wages and the working hours decrease by 1/24 of the current period, then the new cost of erection in Rs. is
A
16,500
B
15,180
C
11,000
D
10,120

Explanation

Correct : b