Mechanical Engineering > GATE 2013 SET-2 > Industrial Engineering
In simple exponential smoothing forecasting, to give higher weightage to recent demand information, the smoothing constant must be close to
A
-1
B
zero
C
0.5
D
1.0

Correct : d

Similar Questions

The actual sales of a product in different months of a particular year are given below: The forecast of the sales, using the 4-month moving average method, f...
#523 Fill in the Blanks
A minimal spanning tree in network flow models involves
#525 MCQ
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4-6 and the project duration, r...
#555 MCQ

Related Topics