Electrical Engineering > GATE 2014 SET-2 > Per Unit System
A three phase star-connected load is drawing power at a voltage of 0.9 pu and 0.8 power factor lagging. The three phase base power and base current are 100 MVA and 437.38 A respectively. The line-to-line load voltage in kV is ________.

Correct : 118.8