EC > GATE 2017 SET-2 > Quantitative Aptitude
1200 men and 500 women can build a bridge in 2 weeks. 900 men and 250 women will take 3 weeks to build the same bridge. How many men will be needed to build the bridge in one week?
Correct : c
Similar Questions
It would take one machine 4 hours to complete a production order and another machine 2 hours to complete the same order. If both machines work simultaneously at...
Two design consultants, P and Q, started working from 8 AM for a client. The client budgeted a total of USD 3000 for the consultants. P stopped working when the...
If the number 715■423 is divisible by 3 (■ denotes the missing digit in the thousandths place), then the smallest whole number in the place of σ...