Computer Sciences > Gate 2015 Set-3 > Software Engineering
Consider a software project with the following information domain characteristic for calculation of function point metric.

    Number of external inputs (I) = 30
    Number of external output (O) = 60
    Number of external inquiries (E) = 23
    Number of files (F) = 08
Number of external interfaces (N) = 02

It is given that the complexity weighting factors for I, O, E, F and N are 4, 5, 4, 10 and 7, respectively. It is also given that, out of fourteen value adjustment factors that influence the development effort, four factors are not applicable, each of he other four factors have value 3, and each of the remaining factors have value 4. The computed value of function point metric is ____________

Correct : a

Similar Questions

Consider the basic COCOMO model where E is the effort applied in person-months, D is the development time in chronological months, KLOC is the estimated number...
#54 MCQ
Consider a software program that is artificially seeded with 100 faults. While testing this program, 159 faults are detected, out of which 75 faults are from th...
#525 Fill in the Blanks
A palindrome is a word that reads the same forwards and backwards. In a game of words, a player has the following two plates painted with letters. From...
#1 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......