Civil Engineering > GATE 2026 SET-2 > Consolidation
For a clayey soil stratum, the time required for degree of consolidation from 25 % to 50 % is 30 days.
The total time (in days) required for 90 % degree of consolidation of the same soil stratum is ______ (rounded off to the nearest integer).

Correct : 129

Similar Questions

The total primary consolidation settlement (Sc) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the c...
#944 Fill in the Blanks
A saturated compressible clay layer of thickness h is sandwiched between two sand layers, as shown in the figure. Initially, the total vertical stress and pore...
#1162 Fill in the Blanks
An undisturbed soil sample was taken from the middle of a clay layer (i.e., 1.5 m below GL), as shown in figure. The water table was at the top of clay layer. L...
#1214 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......