Civil Engineering > GATE 2026 SET-2 > Consolidation
For a clayey soil stratum, the time required for degree of consolidation from 25 % to 50 % is 30 days.
The total time (in days) required for 90 % degree of consolidation of the same soil stratum is ______ (rounded off to the nearest integer).
The total time (in days) required for 90 % degree of consolidation of the same soil stratum is ______ (rounded off to the nearest integer).
Correct : 129