Civil Engineering > GATE 2025 SET-2 > Network Analysis
The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are in the figure.
The total float available for the activity E in day(s) is equal to ______ (round off to the nearest integer).

Correct : 2