Civil Engineering > GATE 2025 SET-1 > CPM/PERT
In the context of construction project management, which of the following statements is/are true:
A
A dummy activity will consume time and resources
B
The programme evaluation and review technique (PERT) is best suited for projects with large uncertainties in the duration of activities
C
A Gantt chart is commonly used for identifying the 'critical path' of activities in a project
D
Free float is the amount of time by which the start of an activity can be delayed without causing a delay in the start of a following activity

Correct : b

Similar Questions

The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P....
#1211 Fill in the Blanks
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding...
#1247 MCQ
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned...