Civil Engineering > GATE 2025 SET-1 > Flood Estimation
A water resources project with an expected life of 25 years has to be designed for an acceptable risk of 5% against a design flood. The return period for the design flood (in years) is ______ (rounded off to the nearest integer).
Correct : 488