Civil Engineering > GATE 2024 SET-2 > Water Treatment
A circular settling tank is to be designed for primary treatment of sewage at a flow rate of 10 million liters/day. Assume a detention period of 2.0 hours and surface loading rate of 40000 liters/m2/day. The height (in meters) of the water column in the tank is _______. (rounded off to 2 decimal places).
Correct : 3.47