Civil Engineering > GATE 2024 SET-2 > Project Crashing
A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
Correct : b
Similar Questions
The matrix P is the inverse of a matrix Q. If I denotes the identity matrix, which one of the following options is correct?
The number of parameters in the univariate exponential and Gaussian distributions, respectively, are
Let x be a continuous variable defined over the interval (−∞,∞), and f(x)=e-x-e-x The integral g(x)=∫f(x)dx is equal to
Total Unique Visitors
Loading......