Civil Engineering > GATE 2024 SET-2 > Project Organization
Consider the statements P and Q.
P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT?
A
Both P and Q are TRUE
B
P is TRUE and Q is FALSE
C
Both P and Q are FALSE
D
P is FALSE and Q is TRUE

Correct : a

Similar Questions

The matrix P is the inverse of a matrix Q. If I denotes the identity matrix, which one of the following options is correct?
#200 MCQ
The number of parameters in the univariate exponential and Gaussian distributions, respectively, are
#201 MCQ
Let x be a continuous variable defined over the interval (−∞,∞), and f(x)=e-x-e-x The integral g(x)=∫f(x)dx is equal to
#202 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......