Civil Engineering > GATE 2024 SET-1 > Hydraulic Jump
A spillway has unit discharge of 7.5 m3/s/m. The flow depth at the downstream horizontal apron is 0.5 m. The tail water depth (in meters) required to form a hydraulic jump is _______. (rounded off to 2 decimal places).

Correct : 2.22

Similar Questions

A hydraulic jump takes place in a 6 m wide rectangular channel at a point where the upstream depth is 0.5 m (just before the jump). If the discharge in the chan...
#1163 Fill in the Blanks
The pre-jump Froude Number for a particular flow in a horizontal rectangular channel is 10. The ratio of sequent depths (i.e., post-jump depth to pre-jump depth...
#1188 Fill in the Blanks
The matrix P is the inverse of a matrix Q. If I denotes the identity matrix, which one of the following options is correct?
#200 MCQ