Civil Engineering > GATE 2024 SET-1 > Consolidation
The total primary consolidation settlement (Sc) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the building, primary consolidation settlement was reported as 10 mm. The additional time (in days) required to achieve 50% of Sc will be _______. (rounded off to the nearest integer).

Correct : 47

Similar Questions

A saturated compressible clay layer of thickness h is sandwiched between two sand layers, as shown in the figure. Initially, the total vertical stress and pore...
#1162 Fill in the Blanks
An undisturbed soil sample was taken from the middle of a clay layer (i.e., 1.5 m below GL), as shown in figure. The water table was at the top of clay layer. L...
#1214 Fill in the Blanks
The results of a consolidation test on an undisturbed soil, sampled at a depth of 10 m below the ground level are as follows: Saturated unit weight 16 kN/m3 P...
#1250 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......