Civil Engineering > GATE 2024 SET-1 > Cost Estimation
Consider the statements P and Q.
P: Client's Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client's Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
A
Both P and Q are TRUE
B
P is TRUE and Q is FALSE
C
Both P and Q are FALSE
D
P is FALSE and Q is TRUE

Correct : d