Civil Engineering > GATE 2022 SET-1 > Construction Management
The project activities are given in the following table along with the duration and dependency.
Which one of the following combinations is correct?

Correct : c
Similar Questions
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be _______.
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types...
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
Total Unique Visitors
Loading......