Civil Engineering > GATE 2022 SET-1 > Construction Management
The project activities are given in the following table along with the duration and dependency.
Which one of the following combinations is correct?
A
Total duration of the project = 22 days, Critical path is Q → S
B
Total duration of the project = 20 days, Critical path is Q → T
C
Total duration of the project = 22 days, Critical path is P → T
D
Total duration of the project = 20 days, Critical path is P → R

Correct : c

Similar Questions

The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be _______.
#244 Fill in the Blanks
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types...
#268 MCQ
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
#283 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......