Civil Engineering > GATE 2021 SET-2 > Construction Management
The activity details for a small project are given in the Table.
The total time (in days, in integer) for project completion is _______.

Correct : 56 to 56

Similar Questions

The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be _______.
#244 Fill in the Blanks
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types...
#268 MCQ
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
#283 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......