Civil Engineering > GATE 2021 SET-1 > Construction Management
A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
The total float of the activity ""V"" (in weeks, in integer) is _______.

Correct : 0 to 0