Civil Engineering > GATE 2021 SET-1 > Construction Management
The direct and indirect costs estimated by a contractor for bidding a project is INR 160000 and INR 20000, respectively. If the mark up applied is 10% of the bid price, the quoted price (in INR) of the contractor is
Correct : a