Civil Engineering > GATE 2020 SET-2 > Surveying
A theodolite is set up at station A. The RL of instrument axis is 212.250 m. The angle of elevation to the top of a 4 m long staff, held vertical at station B, is 7°. The horizontal distance between stations A and B is 400 m. Neglecting the errors due to curvature of earth and refraction, the RL (in m, round off to three decimal places) of station B is _______.

Correct : 257.200 to 257.600

Similar Questions

The accuracy of an Electronic Distance Measuring Instrument (EDMI) is specified as ±(a mm + b ppm) Which one of the following statements is correct?
#217 MCQ
The observed bearings of a traverse are given below: The station(s) most likely to be affected by the local attraction is/are
#234 MCQ
The method of orientation used, when the plane table occupies a position not yet located on the map, is called as
#278 MCQ

Related Topics

theodolite setup station A RL calculation vertical staff angle elevation horizontal distance GATE 2020 civil engineering gate station B RL trigonometry in surveying GATE Civil Engineering 2020 Set-2 surveying calculations

Unique Visitor Count

Total Unique Visitors

Loading......