Civil Engineering > GATE 2020 SET-2 > Construction Materials
Group-I gives a list of test methods for evaluating properties of aggregates. Group-II gives the list of properties to be evaluated.
The correct match of test methods under Group-I to properties under Group-II, is
A
P-4; Q-1; R-2; S-3
B
P-2; Q-1; R-4; S-3
C
P-3; Q-4; R-1; S-2
D
P-2; Q-4; R-3; S-1

Explanation

Correct : b