Civil Engineering > GATE 2020 SET-1 > Highway Engineering
A road in a hilly terrain is to be laid at a gradient of 4.5%. A horizontal curve of radius 100 m is laid at a location on this road. Gradient needs to be eased due to combination of curved horizontal and vertical profiles of the road. As per IRC, the compensated gradient (in %, round off to one decimal place), is _______.
Correct : 4.0 to 4.0
Similar Questions
The following observations are made while testing aggregate for its suitability in pavement construction:
i. Mass of oven-dry aggregate in air = 1000 g
ii. Ma...
A bitumen sample has been graded as VG30 as per IS: 73-2013. The '30' in the grade means that
As per IRC:37-2012, in order to control subgrade rutting in flexible pavements, the parameter to be considered is