Civil Engineering > GATE 2019 SET-2 > Environmental Engineering
A water treatment plant treats 6000 m3 of water per day. As a part of the treatment process, discrete particles are required to be settled in a clarifier. A column test indicates that an overflow rate of 1.5 m per hour would produce the desired removal of particles through settling in the clarifier having a depth of 3.0 m. The volume of the required clarifier (in m3, round off to 1 decimal place) would be _______.
Correct : 495.0 to 505.0