Civil Engineering > GATE 2019 SET-2 > Geotechnical Engineering
Construction of a new building founded on a clayey soil was completed in January 2010. In January 2014, the average consolidation settlement of the foundation in clay was recorded as 10 mm. The ultimate consolidation settlement was estimated in design as 40 mm. Considering double drainage to occur at the clayey soil site, the expected consolidation settlement in January 2019 (in mm, round off to the nearest integer) will be _______.

Correct : 15 to 15

Similar Questions

Group I lists the type of gain or loss of strength in soils. Group II lists the property or process responsible for the loss or gain of strength in soils. T...
#207 MCQ
A soil sample is subjected to a hydrostatic pressure, ฯƒ. The Mohr circle for any point in the soil sample would be
#208 MCQ
A strip footing is resting on the ground surface of a pure clay bed having an undrained cohesion Cu. The ultimate bearing capacity of the footing is equal to
#209 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......