Civil Engineering > GATE 2019 SET-2 > Hydrology
An inflow hydrograph is routed through a reservoir to produce an outflow hydrograph. The peak flow of the inflow hydrograph is PI and the time of occurrence of the peak is tI. The peak flow of the outflow hydrograph is PO and the time of occurrence of the peak is tO. Which one of the following statements is correct?
A
PI < PO and tI < tO
B
PI < PO and tI > tO
C
PI > PO and tI < tO
D
PI > PO and tI > tO

Correct : c

Similar Questions

A confined aquifer of 15 m constant thickness is sandwiched between two aquicludes as shown in the figure (not drawn to scale). The heads indicated by two pi...
#578 Fill in the Blanks
A confined aquifer of 15 m constant thickness is sandwiched between two aquicludes as shown in the figure (not drawn to scale). The heads indicated by two pi...
#578 Fill in the Blanks
A confined aquifer of 15 m constant thickness is sandwiched between two aquicludes as shown in the figure (not drawn to scale). The heads indicated by two pi...
#578 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......