Civil Engineering > GATE 2019 SET-1 > Construction Management
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.
If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be _______.

Correct : 149500 to 149500
Similar Questions
The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be _______.
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types...
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
Total Unique Visitors
Loading......