Civil Engineering > GATE 2019 SET-1 > Hydrology
A catchment may be idealised as a rectangle. There are three rain gauges located inside the catchment at arbitrary locations. The average precipitation over the catchment is estimated by two methods: (i) Arithmetic mean (PA) and (ii) Thiessen polygon (PT). Which one of the following statements is correct?
Correct : d