Civil Engineering > GATE 2018 SET-2 > Environmental Engineering
At a small water treatment plant which has 4 filters, the rates of filtration and backwashing are 200 m3/d/m2 and 1000 m3/d/m2, respectively. Backwashing is done for 15 min per day. The maturation, which occurs initially as the filter is put back into service after cleaning, takes 30 min. It is proposed to recover the water being wasted during backwashing and maturation. The percentage increase in the filtered water produced (up to two decimal places) would be _______.

Correct : 7.75 to 7.95

Similar Questions

A schematic flow diagram of a completely mixed biological reactor with provision for recycling of solids is shown in the figure. S0, S = readily biodegradabl...
#453 Fill in the Blanks
A schematic flow diagram of a completely mixed biological reactor with provision for recycling of solids is shown in the figure. S0, S = readily biodegradabl...
#453 Fill in the Blanks
A schematic flow diagram of a completely mixed biological reactor with provision for recycling of solids is shown in the figure. S0, S = readily biodegradabl...