Civil Engineering > GATE 2018 SET-2 > Irrigation Engineering
The intensity of irrigation for the Kharif season is 50% for an irrigation project with culturable command area of 50,000 hectares. The duty for the Kharif season is 1000 hectare/cumec. Assuming transmission loss of 10%, the required discharge (in cumec, up to two decimal places) at the head of the canal is _______.

Correct : 27.00 to 28.00