For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated as
C0 = -0.25 and C1 = 0.55.
The value of the third coefficient C2 would be _______.
C0 = -0.25 and C1 = 0.55.
The value of the third coefficient C2 would be _______.
Correct : 0.70 to 0.70