Civil Engineering > GATE 2017 SET-2 > Construction Management
Consider the following statements:
P. Walls of one brick thick are measured in square meters.
Q. Walls of one brick thick are measured in cubic meters.
R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 m2 area.
S. For the measurement of excavation from the borrow pit in a fairly uniform ground, deadmen are left at suitable intervals.
For the above statements, the correct option is
A
P-False; Q-True; R-False; S-True
B
P-False; Q-True; R-False; S-False
C
P-True; Q-False; R-True; S-False
D
P-True; Q-False; R-True; S-True

Correct : d

Similar Questions

The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be _______.
#244 Fill in the Blanks
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types...
#268 MCQ
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
#283 Fill in the Blanks

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......