Civil Engineering > GATE 2017 SET-2 > Construction Management
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
A
EPC contract
B
Percentage rate contract
C
Item rate contract
D
Lump sum contract

Correct : d

Similar Questions

The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be _______.
#244 Fill in the Blanks
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
#283 Fill in the Blanks
Consider the following statements: P. Walls of one brick thick are measured in square meters. Q. Walls of one brick thick are measured in cubic meters. R. No...
#298 MCQ

Related Topics

No tags found

Unique Visitor Count

Total Unique Visitors

Loading......