Civil Engineering > GATE 2017 SET-2 > Construction Management
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
A
EPC contract
B
Percentage rate contract
C
Item rate contract
D
Lump sum contract

Explanation

Correct : d