Civil Engineering > GATE 2017 SET-2 > Construction Management
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
A
EPC contract
B
Percentage rate contract
C
Item rate contract
D
Lump sum contract

Correct : d

Similar Questions

The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be _______.
#244 Fill in the Blanks
For a construction project, the mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use t...
#283 Fill in the Blanks
Consider the following statements: P. Walls of one brick thick are measured in square meters. Q. Walls of one brick thick are measured in cubic meters. R. No...
#298 MCQ

Related Topics

civil engineering contracts GATE Civil Engineering 2017 EPC contract percentage rate contract item rate contract lump sum contract construction contracts civil engineering projects

Unique Visitor Count

Total Unique Visitors

Loading......